Most sign shops do not lose money on the sign. They lose it in the week between "looks great" and "that's not what we asked for".
The pattern is familiar. The owner says yes on the phone. The manager sees the proof a week later and wants the logo bigger. The landlord wants a different colour. The letters are already cut. Now everyone remembers the conversation differently, and nobody wrote anything down.
None of this is new, and it is not special to signs. The Project Management Institute has written about it for decades under the name "scope creep", and its 2018 survey found that just over half of completed projects had suffered from uncontrolled changes. The fix is also not new: agree the scope in writing, and handle every change as a change. Here is what that looks like in a sign shop.
1. Put everything on the proof, not just the picture
A proof that only shows the artwork invites argument. A proof that shows the job does not. Every proof should carry:
- The artwork, to scale, on a photo or elevation of the actual wall or site
- Overall size, letter height and depth
- Materials and colours, with paint or vinyl numbers, not "dark blue"
- Lighting: front-lit, halo, or none, and the LED colour
- Mounting method and the install location
- Quantity, job number and revision number
- A short line of what is not included
It takes ten extra minutes. It saves the hour-long phone call later.
2. Say how many revisions are included
Two rounds of changes is a common, fair number. Put it on the quote and on the first proof: "This price includes two rounds of revisions. Further design changes are billed at our design rate." Customers rarely mind. What they mind is a surprise charge at the end.
Number every proof: R1, R2, R3. When someone says "go with the earlier one", everyone knows which one.
3. Get a real approval, not a thumbs-up
A thumbs-up emoji in a chat is friendly. It is not a record. Ask the customer to approve the specific proof, by revision number, with their name and the date. That can be a signature on paper, or a click on an approval page that records who approved what and when.
In the United States, the federal E-SIGN Act says a contract cannot be refused legal effect only because it was signed electronically, so an online approval is a perfectly normal way to do this. The point is not to win in court. The point is that nobody needs to go to court, because the approved proof is right there.
One more thing: make sure the person approving is the person who can approve. In a franchise or a shopping centre, the store manager may love the design while the landlord or head office has the final say. Ask early: "Who else needs to see this before we build it?"
4. Treat every change after approval as a change order
Once the proof is approved, a change is not a favour. It is new work, with a price and maybe a new date. A short change order is enough:
- What changes
- What it costs (or "no charge", written down)
- What it does to the delivery date
- The customer's approval
Many changes will be free, and that is fine. Writing "no charge" still matters, because it shows the customer you did them a favour, and it stops the fifth free change from feeling like a right.
5. Make it easy to say yes quickly
Slow approvals are usually not bad customers. They are busy customers. A few things that help:
- Send the proof with one clear question: "Approve, or tell us what to change."
- Show it on their building, not on a white background. People approve what they can picture.
- Follow up after two working days, then again after four. Politely, and in writing.
- Do not start production on a verbal yes, however friendly the customer is.
The routine in one line
Full proof, numbered revisions, a written approval from the right person, and a change order for anything after. That is all. It feels like paperwork for the first month, and after that it simply feels like how the shop works.
We built the proof and approval step into SignAcctPro for exactly this reason: the customer approves the proof online, the approval is saved with the job, and any change after that becomes a priced change order instead of an argument. If you prefer paper, the same routine works on paper. What matters is that it is the same every time.
Sources and further reading
- Scope Patrol: scope creep is on the rise (PM Network, 2018), Project Management Institute
- Scope change control: control your projects or your projects will control you, Project Management Institute
- Scope creep, not necessarily a bad thing (on written baselines and change documents), Project Management Institute
- 15 U.S. Code § 7001: General rule of validity (E-SIGN Act), Legal Information Institute, Cornell Law School